Close
  • Products
    • All Categories
    • Portable Traffic Signals
    • Temporary Traffic Signals
    • Accessories
    • Trailers
    • Non-Highway Signals
  • Applications
    • 2-Way Shuttle Working
    • Shuttle Working Junctions
    • Complex Urban Junctions
    • Emergency Works
    • Standalone Pedestrian Crossings
    • Arterial / Motorway Junctions
    • Haul Routes, Work Sites & Compounds
  • Support
    • All support
    • Professional Services
    • Service, Maintenance and Repair
    • Signal Hire
    • Downloads
  • Technology
    • Signal Studio
    • TMdesk
    • Active Channel Management
    • AutoGreen Technology
    • Endurance
    • Urban Traffic Control
  • Updates
  • About
    • About Us
    • Our Locations
    • Careers
    • Case Studies
    • Sustainability
  • Contact us

Minimising the impact of Street works in Bristol using UTC portable traffic signals

“The signals improved traffic flow and maximised capacity effectively, minimising the traffic impact of the works.” – Bristol City Council

  • Share via

The Challenge

For traffic control centres around the country, the two main causes of congestion are collisions and roadworks.

Roadworks with temporary traffic signals are a major source of frustration and delay for drivers, and when they are operated in sensitive parts of the network, their impact can be very high. This is especially problematic where the temporary signals are in the middle of a UTC or SCOOT controlled network.

It can be difficult to integrate temporary traffic signals into existing urban traffic control systems. In practice, this means that at highly sensitive sites, Traffic Management (TM) companies are instructed to manually control the signals during the peaks. Officers within the traffic control centres then call the on-site operatives and ask them to adjust the signal timings as required.

This is problematic for the TM companies and contractors due to the staffing cost and for control rooms because coordination between sets of signals is not possible. Also, there can be difficulties in getting hold of the on-site operatives when needed.

Bristol City Council wanted a temporary traffic signal that easily integrated with the existing UTC system and minimised the impact of road works in the city.

The Solution

Traffic Group Signals were the first manufacturer to develop radio-linked temporary traffic signals that operate under UTC control via wireless 3G/4G or ADSL connection.

Our UTC portable traffic signals are capable of operating under UTC fixed time plans, or as part of a SCOOT node. We were able to provide a specialist solution, suited to highly traffic sensitive sites or long term works which allowed the signals to be fully integrated into Bristol’s urban network.

To demonstrate the products capabilities, we trialled our UTC temporary traffic signals at two sites in Bristol and recorded our findings.

“The signals improved traffic flow and maximised capacity effectively, minimising the traffic impact of the works.”


– Bristol City Council

The Results

The trials showed that the signals improved traffic flow and maximised capacity effectively, minimising the traffic impact of the works.

Our UTC temporary signals reduced delay and improved the management of roadworks. They were found to offer a robust alternative to regular temporary traffic signals at problematic sites that are within, or impact on, urban networks.

As a result, Bristol City Council agreed to support the use of our UTC controlled temporary signals at appropriate sites in the future.

Download the White Paper

Download our full white paper, which includes the trial data and full recommendations by Bristol City Council.

Download
WP - Bristol City Council and UTC

Acknowledgements

Special thanks to Bristol City Council for helping us develop this case study, which was awarded Most Innovative Paper at JCT 2015. The original paper can be found here.

Our UTC system was first launched under the Pike Signals brand and formed part of the Evo product line. We continue to support and develop this product, however the branding and compatibility may change over time.

Would you like to work with us?

We are always looking for new stories and case studies for our website. If you’ve had some great results with our products and want us to help you share your success, please send your enquiries to [email protected].

 

  • Discover our UTC offering

    Find out more
  • Speak to an expert

    Get in touch!

Explore related posts

View all
  • Urban Traffic Control

    Tactical Metro Deployment: High-Performance Signalling Over 48 Hours

    Challenge Situated at the bustling intersection where Vauxhall Bridge converges with Millbank in the heart of Central London, Yunex Traffic were tasked with upgrading a junction controller box to...

    Read article
  • Urban Traffic Control

    Using Metro for UTC integrated signalling in Greater Manchester

    Metro has been deployed with wireless UTC integration for a major construction project in Manchester. The Challenge A major construction site in the heart of Manchester required temporary...

    Read article

What are you looking for?

White Lion House,
Gloucester Road,
Cheltenham,
GL51 0TF

Legal
  • Careers
  • Cookie Policy
  • Terms & Conditions
  • Modern Day Slavery and Human Trafficking
  • Privacy Policy
Social
  • X
  • Facebook
  • LinkedIn
Back to top
Want to speak to one of our experts?
Contact us

© 2025 Traffic Group

Traffic Group Signals Ltd reserves the right to change or alter product specifications without prior notice. It is a policy of Traffic Group Signals Ltd to seek Registered Design and/or Patent Protection for its products. Traffic Group Signals is a part of The Traffic Group.

Part of the Traffic Group Logo
Website by Jask Creative